Establishing maintenance schedules for derouging and passivation [Pennsylvania]April 17, 2008 What is the typical frequency for maintenance of WFI piping systems? Is the use of a calendar based preventive maintenance plan typical for addressing rouge buildup and repassivation in these system? Or, is inspection based on some criteria used to determine the need? Evan Schone
April 23, 2008 The answer to your question is not simple, of course. (Is it
ever?) If you use the system for the same hot WFI all the time on the
same schedule, you should be able to put it on the calendar. How
often you need to do it depends on how fast the rouge is appearing,
and how much rouge you want to have before eliminating it.
June 23, 2008 Do you know anyone in the pharmaceutical industry that is not performing derouging passivations? Also do you know if anyone has recevied a 483 for not removing the rouge from there systems? Diana Diana Fischer
![]() |