Letter 20042 Hydrogen embrittlement suspicion [Iran]+++ Piston rod of 1045 steel d=18 mm, l=30 cm should follow the sequences as below: 1-first grinding THE QUESTION IS : SHOULD WE EXPECT HYDROGEN EMBRITTLEMENT AND NEED FOR BAKING? The expert assistance will be appreciated. Hadi Khosravi
+++ Hadi, if it were my part, I would bake it. 150C, for 4 hours, within 4 hours of plating.
+++ Dear Lee, Thank u for respond. I received different answers, the most interesting was by Mr. Guffie through his book : Handbook of Hard Chromium Plating.in page 84 as follows: above 35 rockwell baking required for deposit thicker than0.001 inch. In our line I exactly sticking the boarder line 0.001 or 25 micron .That is why I need more experienced answer hoping get rid of baking facility for 3000 shaft per day. Sorry for late respond, Hadi Khosravi